5,854 MW remaining to the target. Onboard capacity is not a measure of commissioned capacity.
Track Selangor’s green economy transformation across three SAGE volumes, GAPS achievements and delivery milestones towards 2035. Reporting snapshot: 20 October 2026.
5,854 MW remaining to the target. Onboard capacity is not a measure of commissioned capacity.
2035 KPI: 30+ bankable projects across four energy types. Current onboard count includes EV projects.
58 additional charging points needed for the 2026 target.
2,724 additional charging points needed from the current baseline.
Current delivery and target progress
1,560 MW / 7,414 MW by 2035
1,276 installed / 1,334 by 2026
1,276 installed / 4,000 charging points by 2030
300 MW / 3,000 MWac solar potential by 2035
5 projects onboard, including EV · 2027 target intake: 8 projects. Progress bars show the stated capacity or installation baseline against its target, rather than project completion.
Summary of the SAGE journey
Volume 1 official launch · Pulau Indah Power Plant (PIPP) COD · GAPS established
Volumes 2 & 3 soft launch · LSS5 Bestari Jaya official launch · EV charging rollout · GAPS 300 MW
All-volumes publication launch · hydrogen bus pilot · LSS5 COD
4,000 EV charging points targeted · outcome review
7,414 MW energy capacity KPI · 30+ bankable projects across four energy types
From strategic blueprints to statewide outcomes
Develop the strategic blueprints for Volume 2: Circular Economy & Energy Efficiency and Volume 3: Green Mobility; stakeholder validation and strategic framework.
Establish PMO and dashboard; activate Volume 3 initiatives; build investment pipeline; publish first annual report.
Expand high-impact programmes; mobilise financing; integrate programme data; strengthen PBT participation.
Replicate successful projects statewide; commercialise green industry; conduct mid-term review.
Evaluate SAGE 2030 milestones: investment, carbon and employment; refresh the roadmap for 2031–2035.
Generation portfolio · Solar, small hydro, gas CCGT and waste-to-energy
| Project / initiative | Reported capacity | Delivery reference |
|---|---|---|
| LSS5 Floating Solar — Bestari Jaya | 300 MW | Official launch: 2026 · Target COD: 2027 |
| Small Hydro Plant — Kerling Lower & Upper, and Batang Kali | 6.5 MW | Portfolio figure supplied; site capacities require reconciliation |
| Pulau Indah Power Plant (PIPP) | 1,200 MW | Gas CCGT · COD: 2025 |
| WTE Jeram 1, 2 & 3 | 52 MW | Waste-to-energy · COD not specified |
| Solar Commercial & Industrial | 2 MW | Commercial and industrial solar · COD not specified |
CCGT is included in the supplied Clean Energy portfolio; the onboard total should not be interpreted as renewable-only capacity. COD = commercial operation date.
Building the next phase of implementation
Volume 2 is at an early stage. Project scope, implementation milestones and measurable KPIs are to be confirmed.
2026: soft launch of SAGE Volume 2 · 2027: official publication launch alongside all SAGE volumes.
EV charging is currently running · Hydrogen bus pilot targeted for 2027
2026 milestone: EV Charging MOU signing and charging point installation.
Pilot specifications are targets; the hydrogen bus initiative is not presented as operational.
THE SAGE JOURNEY · 2025–2035
Click or tap a year to pin its details below. Hover highlights a year without changing the selected information. Use arrow keys to move, then Enter or Space to select.
Solar development potential and facilitation
2026 achievement: 300 MW and 1,000 acres · 10.0% of the 3 GWac solar potential and 7.7% of the 13,000-acre target. Capacity comparison is indicative pending confirmation of a consistent MW / MWac reporting basis.
Solar development facilitation under SAGE
GAPS established as part of the SAGE programme and as a SAGE catalyst.
2026 achievement under SAGE capacity
Land equivalent for 300 MW of solar development
GAPS supports solar development. The 300 MW achievement is shown separately and is not added to the 1,560 MW onboard total without confirmation of project overlap and capacity accounting.